Where the number comes from
Florida Building Code, Residential: FBC-R 8th edition (2023), Table R301.2(1) and R403.1.4.
Florida measures the 12 inches from finished grade, where the model code measures from undisturbed ground.
Before you dig
- Call 811 a few days ahead. It's free: utilities mark their buried lines before you dig. In Florida, that's Sunshine 811.
- Get the number from your building department. Search its site for a deck or footing handout, or call the permit desk. Ask about the footing size too: the frost depth says how deep, not how wide.
- Measure to the bottom of the footing. From finished grade, after any regrading. The concrete footing sits at the bottom of the hole, so with a 36-inch frost depth the hole itself is at least 36 inches deep.
- Don't skip the inspection. Most towns check the open holes before you pour.
Frost line in nearby states
- Georgia 12 inches, set locally
- Alabama 12 inches, set locally
- South Carolina 12 inches, set locally
- Mississippi no frost depth; footings at least 12 inches deep
- Louisiana no frost depth; footings at least 12 inches deep
- All 50 states and D.C.
Sources
- Florida Building Code, Residential 8th Ed. (2023), R403.1.4 Minimum depth (UpCodes copy)
- FBC-R 8th Ed. Table R301.2(1) (frost line depth cell 'NA', between weathering 'Negligible' and termite 'Very Heavy')
- International Code Council, 2021 International Residential Code, Chapter 4 (R403.1.4 and R403.1.4.1)
- NOAA NCEI, U.S. Climate Normals 1991–2020