What building departments in South Carolina require
Each county or city sets its own frost depth in South Carolina. These are the values their permit handouts and code pages list; yours may differ, so check before you dig.
| Place | Frost depth | Source |
|---|---|---|
| City of Charleston | None listed (footings still 12) | charleston-sc.gov |
| City of Folly Beach | None listed (footings still 12) | cityoffollybeach.com |
| Town of Fort Mill (York County) | 12 inches | fortmillsc.gov |
| Anderson County | 12 inches | andersoncountysc.org |
| Oconee County (mountains) | 12 inches | oconeesc.com |
Where the number comes from
The South Carolina residential code leaves the frost depth for each county or city building department to fill in. That's why the same deck can need deeper footings one town over. (2021 IRC with the SC Building Codes Council's statewide modifications; the frost column of Table R301.2(1) is unmodified.)
Coastal tables (Charleston, Folly Beach) list a frost line of 0. We found nothing published for Columbia or Greenville.
Winter in South Carolina
Averages for Charleston (NOAA 1991–2020 climate normals), the same metro as the South Carolina home maintenance checklist.
- 39°F average low in January, the coldest month
- November 21 first 32°F night of fall, on average
- March 13 last 32°F night of spring, on average
- 0 inches of snow a year
The ground freezes from the top down after weeks of cold and thaws late, often weeks after the last frost. Snow on the ground slows it, while a plowed driveway or a bare, windswept yard freezes deeper. Dig and pour footings before the ground freezes: concrete must never go onto frozen soil, which settles when it thaws.
Before you dig
- Call 811 a few days ahead. It's free: utilities mark their buried lines before you dig. In South Carolina, that's SC811.
- Get the number from your building department. Search its site for a deck or footing handout, or call the permit desk. Ask about the footing size too: the frost depth says how deep, not how wide.
- Measure to the bottom of the footing. From finished grade, after any regrading. The concrete footing sits at the bottom of the hole, so with a 36-inch frost depth the hole itself is at least 36 inches deep.
- Don't skip the inspection. Most towns check the open holes before you pour.
Frost line in nearby states
- North Carolina 12 inches statewide
- Georgia 12 inches, set locally
- Tennessee 12 inches, set locally
- Florida no frost depth; footings at least 12 inches deep
- Virginia 12 to 24 inches, set locally
- All 50 states and D.C.
Sources
- SC Building Codes Council 2024 Final Modification Index
- SC BCC 2021 Modification Index
- SC BCC code adoption page
- City of Charleston: building department
- City of Folly Beach: building department
- Town of Fort Mill (York County): building department
- Anderson County: building department
- Oconee County (mountains): building department
- International Code Council, 2021 International Residential Code, Chapter 4 (R403.1.4 and R403.1.4.1)
- NOAA NCEI, U.S. Climate Normals 1991–2020