What building departments in Pennsylvania require
Each county or city sets its own frost depth in Pennsylvania. These are the values their permit handouts and code pages list; yours may differ, so check before you dig.
| Place | Frost depth | Source |
|---|---|---|
| Philadelphia | 30 inches (2.5 feet) | phila.gov |
| Municipality of Bethel Park (Allegheny County) | 36 inches (3 feet) | ecode360.com |
| Upper Allen Township (Cumberland County) | 36 inches (3 feet) | ecode360.com |
| Schuylkill Township (Chester County) | 36 inches (3 feet) | ecode360.com |
| London Grove Township (Chester County) | 36 inches (3 feet) | ecode360.com |
| Orwigsburg (Schuylkill County) | 36 inches (3 feet) | orwigsburg.gov |
| Millcreek Township (Erie County) | 48 inches (4 feet) | ecode360.com |
| Fairview Township (Erie County) | 48 inches (4 feet) | ecode360.com |
Where the number comes from
The Pennsylvania Uniform Construction Code leaves the frost depth for each county or city building department to fill in. That's why the same deck can need deeper footings one town over. (34 Pa. Code § 403.21; each municipality fills in IRC Table R301.2(1).)
Most municipalities that publish a value use 36 inches. Philadelphia uses 30, and the Erie County townships along the lake use 48.
Winter in Pennsylvania
Averages for Philadelphia (NOAA 1991–2020 climate normals), the same metro as the Pennsylvania home maintenance checklist.
- 27°F average low in January, the coldest month
- November 12 first 32°F night of fall, on average
- April 1 last 32°F night of spring, on average
- 20 inches of snow a year
The ground freezes from the top down after weeks of cold and thaws late, often weeks after the last frost. Snow on the ground slows it, while a plowed driveway or a bare, windswept yard freezes deeper. Dig and pour footings before the ground freezes: concrete must never go onto frozen soil, which settles when it thaws.
Before you dig
- Call 811 a few days ahead. It's free: utilities mark their buried lines before you dig. In Pennsylvania, that's Pennsylvania One Call System (PA811).
- Get the number from your building department. Search its site for a deck or footing handout, or call the permit desk. Ask about the footing size too: the frost depth says how deep, not how wide.
- Measure to the bottom of the footing. From finished grade, after any regrading. The concrete footing sits at the bottom of the hole, so with a 36-inch frost depth the hole itself is at least 36 inches deep.
- Don't skip the inspection. Most towns check the open holes before you pour.
Frost line in nearby states
- New York 42 to 48 inches, set locally
- Maryland 18 to 36 inches, set locally
- Ohio 30 to 42 inches, set locally
- New Jersey 30 to 36 inches by zone
- West Virginia 24 to 32 inches, set locally
- Delaware 24 to 32 inches, set locally
- All 50 states and D.C.
Sources
- 34 Pa. Code § 403.21, Uniform Construction Code (Cornell LII copy)
- Philadelphia Residential Code amendments (2021 IRC), Table R-R301.2(1) frost line depth 30 in.
- Philadelphia: building department
- Municipality of Bethel Park (Allegheny County): building department
- Upper Allen Township (Cumberland County): building department
- Schuylkill Township (Chester County): building department
- London Grove Township (Chester County): building department
- Orwigsburg (Schuylkill County): building department
- Millcreek Township (Erie County): building department
- Fairview Township (Erie County): building department
- International Code Council, 2021 International Residential Code, Chapter 4 (R403.1.4 and R403.1.4.1)
- NOAA NCEI, U.S. Climate Normals 1991–2020