What building departments in New Hampshire require
Each county or city sets its own frost depth in New Hampshire. These are the values their permit handouts and code pages list; yours may differ, so check before you dig.
| Place | Frost depth | Source |
|---|---|---|
| City of Manchester | 48 inches (4 feet) | manchesternh.gov |
| City of Nashua | 48 inches (4 feet) | nashuanh.gov |
| City of Concord | 48 inches (4 feet) | concordnh.gov |
| City of Portsmouth | 48 inches (4 feet) | files.cityofportsmouth.com |
| City of Rochester | 48 inches (4 feet) | rochesternh.gov |
| Town of Londonderry | 48 inches (4 feet) | londonderrynh.gov |
| Town of Bedford | 48 inches (4 feet) | bedfordnh.org |
| City of Lebanon | 48 inches (4 feet) | ecode360.com |
| Town of Hanover | 48 inches (4 feet) | hanovernh.org |
| Town of Alton | 48 inches (4 feet) | alton.nh.gov |
| Town of Moultonborough | 48 inches (4 feet) | moultonboroughnh.gov |
| Town of New Ipswich | 48 inches (4 feet) | newipswichnh.gov |
Where the number comes from
The New Hampshire State Building Code leaves the frost depth for each county or city building department to fill in. That's why the same deck can need deeper footings one town over. (RSA 155-A; each town fills in IRC Table R301.2(1).)
Hanover's 5 feet applies only to commercial buildings. We found no published value for the north country (Berlin, Littleton, Conway).
Winter in New Hampshire
Averages for Manchester (NOAA 1991–2020 climate normals), the same metro as the New Hampshire home maintenance checklist.
- 14°F average low in January, the coldest month
- October 1 first 32°F night of fall, on average
- May 3 last 32°F night of spring, on average
- 56 inches of snow a year
The ground freezes from the top down after weeks of cold and thaws late, often weeks after the last frost. Snow on the ground slows it, while a plowed driveway or a bare, windswept yard freezes deeper. Dig and pour footings before the ground freezes: concrete must never go onto frozen soil, which settles when it thaws.
Before you dig
- Call 811 a few days ahead. It's free: utilities mark their buried lines before you dig. In New Hampshire, that's Dig Safe 811 (serves New Hampshire).
- Get the number from your building department. Search its site for a deck or footing handout, or call the permit desk. Ask about the footing size too: the frost depth says how deep, not how wide.
- Measure to the bottom of the footing. From finished grade, after any regrading. The concrete footing sits at the bottom of the hole, so with a 36-inch frost depth the hole itself is at least 36 inches deep.
- Don't skip the inspection. Most towns check the open holes before you pour.
Frost line in nearby states
- Maine 48 to 60 inches, set locally
- Vermont no state code for houses; 60 inches for public and rental buildings
- Massachusetts 48 inches statewide
- New York 42 to 48 inches, set locally
- Connecticut 42 inches statewide
- All 50 states and D.C.
Sources
- Building Code of the City of Manchester (adopted July 6, 2021), Table R301.2(1) frost line depth 4'0"
- Nashua Ordinance O-21-045 (frost-line depth minimum 48 in)
- Concord Residential Building Permit Application Guide (48 in)
- Portsmouth Ordinance Ch. 12, IRC 2015 amendments (4 ft)
- Rochester deck handout, 2018 IRC (48 in)
- Hanover Building Code Adopting Ordinance 2023 (4 ft residential, 5 ft IBC)
- Town of Londonderry: building department
- Town of Bedford: building department
- City of Lebanon: building department
- Town of Alton: building department
- Town of Moultonborough: building department
- Town of New Ipswich: building department
- International Code Council, 2021 International Residential Code, Chapter 4 (R403.1.4 and R403.1.4.1)
- NOAA NCEI, U.S. Climate Normals 1991–2020